Project Page

Current Status
 

9/18/2017

Bartlett and Cocke General Contractors – CCHS & Gym

Drywall at Area B Auditorium, 95%, water proofing Area F, complete.  Area A composite panel installation, 90%, Area F metal panels underway.  Area f smooth CMU complete, Tape/Float/ Paint Area A Rotunda and C underway.  Quarry tile at kitchen complete, laminate wall panels at cafeteria 95%, Millwork underway at Area A.  Fire pump installation complete; AEP is working on job details, Texas scenic rigging/battens 85%.  Above ceiling items Area C/F underway, Area E electric in-wall passed, plumbing underway, flatwork at main entrance, and main parking underway.

 

Sterling Fly JH

Stanley Security 90%, Trane controls in progress an 1 bad AC compressor is being replaced.

 

Benito Juarez MS

Slab pour complete, forms have been wrecked, forming connection slab and ramp on-going. 

 

9/13/2017           

Ribbon Cutting – Sterling H. Fly Jr. High School

Ribbon Cutting Ceremony was held on Wednesday, September 13, 2017 at 5:00 p.m.

 

9/8/2017

Bartlett and Cocke General Contractors – CCHS & Gym

Benito Juarez MS addition: Pour concrete slab, strip forms and install clay cap.

 

9/5/2017

Bartlett and Cocke General Contractors – CCHS & Gym Recent Progress/Current Activities.  Drywall area E, 70%, waterproofing Area E underway, Area A composite panel installation, 60%.  Area F smooth CMU, 65%, tape/float/texture/paint Area B/C underway.  Quarry tile at kitchen, 95%, fire pump installation underway, Area E electrical in-wall passed, plumbing underway and Flatwork at Area B started.

 

Fly Building: exterior handrails, 2 speakers, intercom items.

 

Benito Juarez MS addition: Beam excavation, form and tie rebar.

 

Existing Gym: Mostly completed – Ceiling lights, Office, entry hall, showers, dressing room, electrical and plumbing completed.  Water heaters and instrumentation completed.

 

8/28/2017           

Bartlett and Cocke General Contractors have officially release the new Fly Building to the CCISD for moving furniture and equipment.

 

7/6/2017

Bartlett and Cocke General Contractors - Crystal City ISD Project Status.

Click link

 Construction Status July 6, 2017

 

6/26/2017

Bartlett and Cocke General Contractors - Crystal City ISD Project Status.

CCHS & CCHS Gym:  Interior framing at C/E underway, waterproofing Area C/E/F, and aluminum storefronts Area E underway.  Area B R-panels underway, Area B stone installation, In-wall blocking Area C underway. Tape/float/texture Area A underway.  MEP rough in underway Area B/C/F, early establishment of electrical rooms in all area underway, and fire sprinkler Area A/F underway.   Finish grading /clay cap 85% complete, drywall paint in cafeteria and auditorium complete, and fire sprinklers in Area G 70% complete.

 

Fly:  MEP inspection today, Tape, float and texture drywall complete, primer and first coat of paint complete, electrical above ceiling rough-in on-going at kitchen and cafeteria.  HVAC supply flex installation on-going, Data cabling on-going, final roof cap installation on-going.  Fire Alarm cabling on-going, quarry tile in kitchen installation complete, ceramic wall tile on-going.  Suspended ceiling installation on-going and install storefront doors underway.

 

6/3/2017

Bartlett and Cocke General Contractors - Crystal City ISD Project Status.

Click link

Construction Status June 23, 2017

 

5/15//2017

Bartlett and Cocke General Contractors - Crystal City ISD Project Status.

CCHS & CCHS Gym:  Exterior framing at Area F underway, interior framing at Area A/B/C underway, and sheetrock Area A underway.  Roof clocking Area E 90% complete, Area F roof complete, waterproofing Area C/E underway, Aluminum storefronts Area C complete,  Area B R-panels underway, Area A stone 65% complete, Area C underway.  Mechanical duct work Area A/B/C underway, overhead electrical rough in on-going, plumbing top out in Area C/F, fire sprinkler Area C underway and finish grading / clay cap underway.

 

Fly:  Metal panels and trim installation on roof side, tape, float and texture drywall 95% complete, primer and first coat of paint complete.  Electrical above ceiling rough-in on-going, HVAC supply flex installation on-going, plaster installation complete.  Data cabling on-going, final roof cap installation on-going, Form, inspect, pour transformer pad and switchgear pad, pulling alarm cable on-going, and suspended ceiling installation is on-going.

 

4/18/2017

Bartlett and Cocke General Contractors - Crystal City ISD Project Status.

CCHS & CCHS Gym:  Decking /detailing at Areas F& E underway, interior framing at A/B/C underway, Exterior CMU at Area F 90% complete.  Roof blocking Area F underway.  Waterproofing in Area B underway, Aluminum storefronts Area A underway, Area A stone underway, Electrical in-wall rough-in underway Area B/C/F.  Plumbing top out Area B/C/F and fire sprinkler system Area A/B underway.

Area F roof started and RTU’s set.

Fly:  Interior sheet rock installation 95% complete, waterproofing and thru-wall flashing exterior walls completed.  Metal panels and trim installation is on-going, tape, float, and texture drywall is on-going.  Primer and first coat of paint started, exterior window framing and glazing installation complete and waiting on storefront doors.  Electrical above ceiling rough-in on-going, HVAC supply flex installation on-going and metal lath installation is also on-going.

 

4/04/2017

Bartlett and Cocke General Contractors - Crystal City ISD Project Status.

CCHS & CCHS Gym:  Decking /detailing at Areas F& E underway, exterior framing C 90%, exterior CMU at Area F underway, roof blocking Area C underway and Area B roof complete. Waterproofing Area A underway, Aluminum storefronts Area A underway.  Area B Auditorium elevated platform underway, mechanical in-wall rough –in underway, electrical in-wall/plumbing top out Area F underway.  Plumbing overhead 90% at Area A, plumbing top out in Areas B & C underway and fire sprinkler Area A 80% complete.

 

Fly:  Interior sheet rock installation – Administration Area 90% complete, waterproofing and thru-wall flashing exterior walls underway, metal panels and trim on-going.  Tape, float drywall, exterior brick complete, exterior window framing and glazing installation on-going.  Electrical wall rough-in inspection with City complete.  Brick at stage underway and installation of Z’s for plaster installation started.

 

3/22/2017

Bartlett and Cocke General Contractors: Access Control/ Security Coordination Meeting .

Discuss rough in required for access control hardware.

 

3/10/2017

Bartlett and Cocke General Contractors - Crystal City ISD Project Status.

 

IMPORTANT NOTICE: Once you click on any one of the following links, you will leave this website. Please note that we are not responsible for any content posted on these websites or the design of these websites.

 

Click on the link below to watch the video

  https://youtu.be/Jpu-PBVvea4

 

3/8/2017

Regular School Board Meeting

Action Item 8.F

Consider approval of Bartlett and Cocke GMP for the Benito Juarez MS addition under the Construction 2015.    

The Board of Trustees tabled Item 8.F.

 

3/8/2017

Bartlett and Cocke General Contractors:   See links below:

 

3-2-2017 CCHS Project Status.pdf

and

 

3-2-2017 Fly Project Status Photos.pdf

 

2/27/2017

Bartlett and Cocke General Contractors:  

CCHS - Area B additional built up areas, and 2nd level control room.

Fly Jr. High - Exterior brick on-going.

 

2/23/2017

Bartlett and Cocke General Contractors:  

CCHS  & GYM – Area B Steel detailing underway, PEMB at Area F, 80% complete, Decking at rotunda Area A underway, Area B control room, and concrete ramps complete, Exterior framing / sheathing Area A underway, Interior framing Area A underway, CMU at Area A kitchen complete, Roof blocking Area A underway,  Roofing at Area A, Ductwork at Area A underway, Permanent transformer set Area F Gym, AEP, Electrical in-wall rough in underway Area A and Plumbing mains at Area A.

Fly Jr. High – Interior metal stud and door frame installation complete by week end, Fur down framing has begun, Waterproofing and flashing exterior walls compete by end of week, Wood blocking for cabinets complete, Roof is dried-in; final cap sheets will be installed after RTU’s, Exterior brick on-going, Ductwork installation complete by 2/28 and MEP top-out by 3/3.

 

2/4/2016

Bartlett and Cocke General Contractors:  Electricians cutting power off at 7:00 am for work on panel box.

Power was restored at 10:38 am.

 
12/27/2016
Bartlett and Cocke General Contractors:  CCHS- Area A Steel begins
Sterling Fly Jr. High School:  Installing joist bridging, installing metal decks, installing metal stud clips, laying masonry block, 
 
12/22/2016
Bartlett and Cocke General Contractors: CCHS- Complete columns Area A Kitchen
 
12/21/2016
Bartlett and Cocke General Contractors: CCHS- Pour # 9 Area E1, Electrical /Plumbing Rough In at Area F complete, Plumbing top out underway at Area A, Mock-up wall window flashing complete, Marquee footing complete, Pump house slab 90%.
Sterling Fly Jr. High School:  Installing joist bridging, installing metal decks, installing metal stud clips, laying masonry block, MEP rough-in at block walls, Wrecking pans under slab, forming two stoop extensions.
 

12/19/2017

Bartlett and Cocke General Contractors:  Sterling Fly – Masonry block has started. Metal stud framing has started

 

12/7/2016

Bartlett and Cocke General Contractors:   Pour # 8 Area C2, Marquee footing 90% complete

 

12/6/2016

Bartlett and Cocke General Contractors:  CCHS -  Dewatering at entire site, Area A Kitchen /Area B Columns underway,  Electrical / Plumbing Rough In at Area F underway, Mock-up wall stone, brick and glazing installation completed.  Area E concrete slab completed.  Area C concrete columns completed. Completed Area F Plumbing /Electrical in-slab.  Area A steel.   Sterling Fly – Slab pours, Columns completed, structural steel continues, stripping of shoring, pans and forms.

 
 
 

11/8/2016

Bartlett and Cocke General Contractors:  Urban Concrete Co.  - Concrete pour at south half SFJH.  Rebar installation ongoing at SFJH.

 

11/3/2016

Bartlett and Cocke General Contractors:  Reinforcing inspection conducted at SFJH

(CCHS) MEP rough-in is on-going at the main kitchen area. Rebar installation will begin for concrete the week of 11/7.  Beam dig is complete at area C.  Rebar installation will begin in prep for concrete the week of 11/7.

 

11/1/2016

Bartlett and Cocke General Contractors:  Urban Concrete Co.  - Pan and rebar installation is complete at the south half of SFJH.  Pan and rebar installation on-going for the north portion of SFJH.

 

10/30/2016

Bartlett and Cocke General Contractors:  Pour completed for Area B Stage and Alternate 1.5  Concrete columns in Area A. 14 columns poured

 

 

10/18/2016
Bartlett and Cocke General Contractors:
CCHS:
Pour # 3 Rotunda, complete; Building Pad F, complete
Plumbing in-slab rough in rework underway
Plumbing/ Electrical in – slab rough in Area C underway
Mock-up slab, frame, and sheath, complete
Sterling Fly:
Drill and pour piers – Piers complete
Pour mud slab fly kitchen area today.
Shoring and decking on-going

 

10/8/2016
Bartlett and Cocke General Contractors:
Electrical repairs at Band Hall feeders complete.

  

9/19/2016

Bartlett and Cocke General Contractors:

High School and Gym:

Beam digging underway; Area A - pour concrete # scheduled for 10/5/16

Building Pad F; 30%

Electrical repairs at the Band Hall feeders underway.

Sterling Fly:

Drill and pour piers - 42 piers with extensions completed to date

Form & Tie rebar at the deep sump pit

Form & Tie rebar at the SW sump pit

Prep subgrade at the SW for mud slab

Install 6' SS along Crockett Stree

Form storm drain culvert at sidewalk along SW of football practice field

 

9/19/2016

Bartlett and Cocke General Contractors:

High School and Gym:

Beam digging underway; Area A - pour concrete #1 complete

Building Pad C & E completed

Excavation of Area F (new gym) underway; waiting on electrical and fiber re-route

Parking lot build up - first lift; 80% complete

Site utilities; complete, testing follows

Plumbing /electrical in-slab rough in Area A; complete

Plumbing /electrical in-slab rough in Area A, Kitchen underway; 45% complete

Sterling Fly:

Drill and pour piers - 15 piers completed to date

Form and pour extensions

Excavation of deep beam

 

9/14/2016

Bartlett and Cocke General Contractors: Urban Concrete starts digging for piers at Fly. 

Urban Concrete starts digging for piers at Fly.  J&J Excavation at the new gym site using heavy equipment to dig 11 feet into ground and remove dirt

 

9/13/2016

Bartlett and Cocke General Contractors – Culvert work on rip-wrap near completion.   Urban Concrete is starting in Area A only and then they will move to rea B & E.  Transformer at new gym site will have to be relocated.  Fiber optic line at SW corner of Field house will have to be re-routed.    The under floor crawl space fine grading has been completed at the Fly new building site.

 

9/12/2016

Bartlett and Cocke General Contractors – Area A in-slab plumbing rough-in completed.  Area A in-slab electrical is underway.  J & J Excavation Company is rebuilding pad C & E.  J & J Excavation is grading the parking areas.

 

9/9/2016

Bartlett and Cocke General Contractors – J & J Excavation:  Demolition of concrete drive ways has been completed.

 

9/8/2016

Sterling Fly

Bartlett and Cocke General Contractors- Hydro Excavation at the Sterling Fly completed.  Under floor crawl space fine grading has been completed.

 

9/2/2016

Bartlett and Cocke General Contractors - Installation of AT&T conduits have been completed at Sterling Fly, Area B plumbing in-slab rough –in completed.  J& J Excavation at the new gym site started.  Site Utilities for the High School are at 90% completion.  (This includes water utilities)

 
8/30/2016
Bartlett and Cocke General Contractors - In-Slab electrical work in Area A is in progress.  Conduits from the Existing Gym to the Bandhall are at 90%.  J&J Excavation is at 90% completion with excavation at the Fly new building area.
 
8/26/2016
Bartlett and Cocke General Contractors - Pad C & E are being refilled with select fill material
 
8/24/2016
School Board - Special Session
Action Item 7.F
Consider approval of guaranteed maximum price to the building package of construction 2015 and issue notice to proceed with the construction.
 
8/22/2016
Bartlett and Cocke General Contractors - Drying out excavated areas. The covert on Popeye lane has temporary metal plates for traffic to pass over.
 
8/15/2016
Bartlett and Cocke General Contractors - Excavation and rebuild pads are closed due to Rain.  (8/15 thru 8/19th)
Some Electrical work at the existing gym is in progress
 
8/8/2016
Bartlett and Cocke General Contractors - Water/Fire Line:  Boring and pipeline set under 7th Avenue.  The water line has been tapped into the City main line at 7th Avenue. Domestic and Fire lines are 60% installed.
 
 8/5/2016
Bartlett and Cocke General Contractors - Completed excavation of building C& E.  Electrical infrastructure of the high school gymnasium transformer pad has been completed.  Water lines (fire line) work is at 30% completed, boring at 7th Avenue has been completed.  Footing for box coverts are completed at Popeye Lane and crews are working on the walls.  Plumbing rough-in at building B and at the Alternate Area 1.5 are at 88% complete.  The Remodel work continues at the Fly Sterling:  exterior door cut-in, door installs, electrical wiring and painting.  Safety door closures are being installed at the Fly Sterling  and Gym. 
 
8/3/2016
Bartlett and Cocke General Contractors - Excavation at Sterling Fly.  Removing old building footings. Clean out opening under Sterling building.
 
7/28/2016
Bartlett and Cocke General Contractors - Pre-proposal conference 10:00am at Bartlett and Cocke's San Antonio Office and 2:00pm at Crystal City ISD Administration Office.
 
7/27/2016
Bartlett and Cocke General Contractors -  Excavation for north side Transformer and trenching for the high school parking area light poles begins.
 
7/26/2016
Bartlett and Cocke General Contractors - Trenching for the data conduit for the new gym begins.
 
7/21/2016
Status - Photos, see link below titled:  CCISD 2015 Bond Status Photos 7-21-16
 
7/19/2016
Bartlett and Cocke General Contractors - Storm Sewer work, 8ft box coverts at Popeye Lane started.
 
6/29/2016
Bartlett and Cocke General Contractors - J&J Excavation: Structural building fill and pack started.  Temporary transformer pad completed.
 
6/28/2016
Bartlett and Cocke General Contractors - Structural building cut for Sections A, B and C partial have been completed.
 
6/22/2016
Bartlett and Cocke General Contractors - Electrical transformer pad for the south side of the high school for permanent power.
 
6/20/2016
Bartlett and Cocke General Contractors - Storm Sewer and boxes project, Sanitary Sewer project started.

6/13/2016

Bartlett and Cocke General Contractors - J&J Excavation: Structural building excavating, rough in, pad cut for building sections A, B and C begins.

 

6/8/2016

Regular School Board Meeting - 6:00pm

Action Item 8.F

Consider approval to contract for construction materials engineering, testing and inspection services and the verification testing services necessary for acceptance of the facility by the District.

(Approved)

 

6/8/2016

Bartlett and Cocke General Contractors - Electrical conduit work at existing high school, underground conduits to West Wing.  Electrical panel boxes installed and temporary pad for new transformer.

 

6/8/2016

Groundbreaking Ceremony at the Crystal City High School Complex area off 7th Street, Wednesday, June 8th at 5:00pm.  You may park a the Nutrition Center parking lot and walk, or drive in through the gates next to the basketball courts at the complex area.

 

6/6/2016

Bartlett and Cocke General Contractors - Started concrete demolition at High School rear area and at the drive way south of the West Wing.  Contractors are excavating the area between the Marilu Massignani building and the Nutrition Center for a retention pond.

 

5/30/2016

Bartlett and Cocke General Contractors - Mobilization of Heavy Equipment from J&J Excavation, hardware and supplies stored at the construction site.

 

5/25/2016

Special Board Meeting

Action Item 5.A

Consider approval of Construction Manager at-Risk's Guaranteed Maximum Price Proposal for the 2015 Bond Site Package.

(Approved)

 

5/24/2016

Bartlett and Cocke General Contractors began fencing around the new high school construction area located between the existing high school, west wing, Massignani building and sports complex.

 

5/5/2016

Bids Due at 2:00 PM

 

4/25/2016

Bartlett and Cocke General Contractors Meeting - Review Stanely entry door systems, WIQ system, and the Aiphone door station.

Reviewed Auditorium stage equipment, Food Service equipment and Technology data and fiber conduit locations.

 

4/18/2016

Pre-Proposal Meeting in CCISD Board Room with Site Visit to follow.

 

4/12/2016

Drawing & Specifications available.

 

3/25/2016

Take Tours of New High School and Sterling Fly Building

 

 3/7/2016

Bartlett and Cocke General Contractors began the demolition of old Crystal City High School building on E. Crockett and 7th Avenue.

 

2/24/2016

Special Board Meeting

Action Item 5.A

Review and consider approval of Construction Manager's presentation on cost proposal and approval to proceed with Architect's design development drawings for Crystal City High School, Sterling Fly Jr. High and Benito Juarez Middle School.

 

2/19/2016 

Advertisement and Web posting.

School Construction Bid Opportunities - Attention Vendors! Bartlett and Cocke General Contractors wants to meet you!  Contact us today!   See Flyer (School Const_Bid Op.pdf) below for details.

 

2/18/2016

Construction meeting at Bartlett & Cocke General Contractors to discuss key budget items.

 

2/10/2016

Regular School Board Meeting

Action Item 7.C

Consider approval of the prevailing wage lists by the U.S. Dept. Of Labor for Building, Heavy, and Highway construction for calendar year 2016 for Construction 2015 projects.  (Approved)

 

Action Item 7.F

Consider to approve the Guaranteed Maximum Price Amendment to the Construction Manager at Risk contract for the Sterling H. Fly Junior High Annex demolition package, and authorize the school administration to issue a notice to proceed letter to Bartlett Cocke General Contractors for the work.    (Approved)

 

2/10/2016

Asbestos removal started at the Annex Building (Fly JHS).  Jupe Environmental.  Completion Date: 2/12/2016

 

2/8/2016 Meeting at Crystal City ISD with Pfluger Architects and Bartlett & Cocke GC.

 

2/4/2016

Receive Proposals from Subs & Suppliers at Bartlett & Cocke General Contractors Office by 2:00 pm.

 

1/29/2016

Early Demo meeting at the Fly Jr. High Annex.  CCISD and Bartlett and Cocke GM discussed Plans for distribution, advertisement, Pre-proposal conference, Proposals due to Bartlett and Cocke G.C. and Demo start date.

1/28/2016

Meeting with CCISD, MFP and Flexile Systems at Felxile Systems' Office.  Document Data drops for Classrooms, Offices and Labs. Discuss fiber optics pathways and Copper Cable Plant. Discuss options for  Intercom, Media projectors and sound systems.

 

1/26/2016

Meeting with CCISD, MEP, Pfluger and Associates and Bartlett Cocke General Contractor - Design and Development, discuss soil samples and type of foundation method of construction. 

 

1/22/2016

On Site meeting with CCISD, Bartlett Cocke General Contractor and L & T Masonry, Inc. to discuss masonry and brick material type and thickness, salvage brick panels. 

 

1/11/2016

On Site meeting with CCISD, AEP, MEP, Pfluger and Associates and Bartlett Cocke General Contractor to review site Transformers, temporary transformer locations, Utility Poles and Electrical Power Panels.

 

1/5/2016

Meeting in San Antonio at the office of Bartlett Cocke General Contractor to do final revisions with Pfluger and Associates on CCHS and Fly buildings.  Go over Early Demo, Site, and Utilities & Under-slab, MEP Package – Preliminary.  10:00am – 4:00pm

 

9/22/2015

Facility Planning Committee Meeting 

 

Pfluger Architects met with Sterling Fly Jr. High School staff to go over the facility schematic design and recommend changes or reworks.

 

Pfluger Architects met with Crystal City High School staff to go over the facility schematic design.

Discuss and reach decisions.

 

 

10/14/2015

Action Item 7.G

Consider approval of the prevailing wages list by U.S. Dept. of Labor for construction 2015 project.

 

9/9/2015

Crystal City ISD has hired Bartelett Cocke General Contractors, LLC for the Construction Manager at Risk.

See Construction Manager at Risk Evaluation - Score for Construction 2015, listed below.

 

9/1/2015

Architectural Meeting – Pfluger Architects met with Crystal City High School Staff to discuss staff member’s input and feedback on the design phase of the new building.

 

7/15/2015

The Crystal City ISD Board of Trustees have hired the Civil Engineering Consultants firm for all civil engineering.

 

7/15/2015

The Crystal City ISD Board of Trustees have selected the Construction Manager at Risk as the construction method(s) for the upcoming projects.

 

5/18/2015

Special School Board Meeting

Consideration and Approval of an Order Canvassing Bond Election Returns

Board President Mr. Espinosa reported the summary of precinct returns of May 9, 2015 Bond Election and certified that the total of all votes received "for" and "against" each measure correspond to votes shown by the precinct returns.

 

Bond Election         For:           850

                             Against:    350

 

5/9/2015

Bond Election

 

4/21/2015

Public Hearing

The Crystal City ISD held a Public Hearing for the purpose of informing the public on the specifics of the bond election.  Business Manager Robert Velasquez provided the public with facts abut the proposed construction and renovation projects for the different campuses within the district.  The project calls for a new main high school building and a the Sterling Fly Jr. High School, a new building will replace the aging "Annex" building. The Benito Juarez Middle School will have new science lab and music building.  The Dr. Tomas Rivera Elementary will get new Gym.